- * guaranteed values designed for the planned load (material and hydraulic load may oscillate between 30 - 100 % of the capacity)
6.4 Noise level
The only source of noise in a WWTP is the membrane-air pump. For additional information concerning the noise level - see the membrane-air pump manual.
- 7. Putting the WWTP into operation
7.1 Duties of an authorized seller
Authorized sellers who are trained by the WWTP manufacturer and entrusted with distribution and assembly of the WWTP are obliged to provide:
o transport
o installation
o covering of the basin
o assembly of the WWTP and its connection
o putting the WWTP into operation, testing and setting of the device
o pass the WWTP over to the customer
7.1.1 Manipulation and transport
The WWTP can be loaded on a means of transport using a high lift truck or manually. Neither binding, nor any suspension is required. The WWTP is transported on a truck or on a sidecar. When transporting, the WWTP must be fastened to ensure that it does not shift. The installation may be done manually.
- 7.1.2 Installation
It is possible to install the WWTP below the ground level without any further static securing under the following conditions:
o the external earth pressure load of the basin will not exceed that of loose soil &Mac179; = 1.7 t/m3, = 35o,
o the basin will be installed on a reinforced flat concrete slab, 100 mm thick,
o the slab will be reinforced by a reinforcing net,
o the underground water level will be lowered below the level of the underside of footing.
The travel overload near the WWTP is not taken into consideration.
In other cases the basin must be embedded in concrete to secure additional static securing.
- 7.1.3 Covering of the basin, access to the basin
A removable wooden or laminate covering may be ordered. The covering must not be walked on. The WWTP covering can be also solved in a different way within the Project provided that the following conditions are followed:
1. the covering must enable the access to the entire WWTP platform
2. the covering must enable a safe access to the WWTP in accordance with valid safety regulations
3. the covering must follow valid safety regulations and ensure that nobody will fall into the basin.
In cases where the top edge of the WWTP is below the ground level, the service and common maintenance can be done without entering the basin. If the WWTP is installed deeper, the access into the basin must be solved in the Project and must follow valid safety regulations. The inner parts of the WWTP are not designed to be walked on.
- 7.1.4 Connection of the WWTP
The membrane air-pump is connected to the socket of the electro-box. This box comes as part of the delivery. The electro-box and the membrane-air pump must be placed inside a covered object near the WWTP (a cellar, garage). To connect this electro-box, an outlet minimum 3 x 1.5 mm2 for a CYKY cable must be prepared. For types BC 4 and 8 this cable is secured by a separated circuit breaker in the main switch-board of the object 230 V/ 1.5 A (230V/2A for types BC 12 and 15). The socket, which is part of the delivered electro-box, must be installed on a firm base (e.g. a wall).
The forced-air piping of the membrane pump is connected with the WWTP by a _ PVC hose; this hose is laid in the same excavation pit together with the inlet waste water piping. The piping must be laid in a plastic or steel protector with a minimum diameter of 60 mm. PE hoses for the electromagnetic valves in the electro-box will be inserted in this protector as well.
The WWTP is devised to work in humid conditions and in conditions with deleterious effects in accordance with Czech Standard _SN 33 2000-3, specifically those conditions coded by the following number-letter combinations: AA 4, AA 6, AB 4, AB 6, AD 4, AF 3.
- 7.1.5 Assembly instructions
The WWTP is installed on a flat concrete bottom in a pit, and thereafter levelling must be checked. The WWTP is installed in such a fashion that the detritus trap points to the waste water piping supply
inlet. Up to approx. one third of the WWTP is filled with water. The inlet hole for the incoming waste-water piping is marked and the inlet into the WWTP is created and sealed.
The membrane air-pump is installed inside a covered object, connected to the electro-box via a socket, and all the functions must then be tested. The membrane pump is connected with the air distributor via a PVC hose. A branch is installed between the air distributor and the membrane pump. This branch is connected to the electro-box via a PE hose. The remaining hydraulic-pneumatic pumps and the electro-magnetic valves are connected from the electro-box.
The outlet piping is connected to the final clarification zone of the WWTP and all the slots are tightened. Subsequently, the WWTP is gradually filled with water or with activated sludge, while simultaneously creating an envelope of saturated soil around it, afterwards checking the basin's water impermeability. The soil envelope is done in accordance with Assembly Regulations for implementing soil envelopes and laying concrete.
7.1.6 Putting into operation, testing, and setting up
On the air distributor, the amount of air-supply for the hydraulic-pneumatic pump (a mammoth) and the amount of air-supply under the detritus trap of the mechanical pre-treatment is adjusted. The mammoth of the recirculation pump is pre-set to such a rating, so that 1/3 - 1/2 of the pipe is filled with the recirculated activated mixture.
The amount of air-supply under the detritus trap must be adjusted in such a manner that a bubble appears every second. The air-supply inlet into the aeration elements is fully open.
The first thing to adjust on the control unit is to set the membrane pump to unintermittent mode using mode A - code 9 - see 8.1.3. The WWTP is regularly inspected, and the membrane pump, air-supply for particular parts as well as the quality of the purified water are checked. If necessary, the performance of the membrane pump is regulated using the control unit BCC-02.
7.1.7 Passing the WWTP to the customer
The WWTP is passed over to the customer en mass, e.g. when the technological part is installed in the basin. The membrane pump and the electro-box are delivered separately. It is also possible to deliver the technological equipment without the basin; in this case the WWTP is installed in a concrete basin, and the final clarification basin, the aeration system, and the air distributor are delivered separately
- 7.2 Operator's duties
The operator is obliged to ensure a suitable location for installation of the membrane pump and of the electro-box. The electro-box and the membrane pump must be installed inside a covered object near the WWTP (e.g. basement, garage, etc.) To connect this electro-box to the grid, an outlet of minimum 3 x 1.5 mm2 for a CYKY cable must be prepared. For types BC 4 and 8 this cable is secured by a separate circuit breaker in the main switch-board of the object 230 V/ 1.5 A (230 V/ 2 A for types BC 12
and 15).
Before the WWTP is put into operation, the operator is obliged to fill the WWTP with the required volume of clean water.
- 7.3 Putting into operation
To ensure the required quality of waste-water, it is necessary to start the biological process. This can be done in the following two ways:
1) Gradual start, the so-called volume-inflow of waste water and by permanent loading of the WWTP, even over the level of set technological parameters.
2) Supply of inoculate sludge.
In both cases the membrane air-pump and all components of the aeration and technological equipment (as well as the hydraulic-pneumatic pump) must work uninterrupted, using the appropriate control unit setting - mode A, code 9. It takes from 3 to 8 weeks to start the whole process gradually and is dependant on waste-water quality and it's temperature.
After the WWTP is broken in, the code in mode A is switched over to intermittent service. This is done based on the measurement of the level of concentration of dissolved O2 in the inlet zone and in the activation zone of the WWTP. Adjustment of the working time and intermissions depends on the actual material and hydraulic loading during a long-term monitoring of the WWTP. We recommend that monitoring should be done by an authorized seller or by the manufacturer.
Using inoculate sludge
A sample of inoculate sludge is imported from an efficient biological WWTP. The WWTP is broken-in in the following way:
1. A particular WWTP with good quality flocculating activated sludge is chosen.
2. Recent results of sludge tests are evaluated: sedimentation, undissolved material, sludge index; New tests are conducted and the above-mentioned parameters, including biological evaluation, are re- measured.
3. A cesspool age truck sucks condensed activating sludge, preferably from the recirculation piping of the final clarification basin. It is possible to take mechanically-concentrated activated sludge from the de-watering device of the WWTP in the amount of 20 - 30 kg (dry sludge approx. 25%).
4. The imported inoculate sludge is discharged into the activation zone of the basin. If mechanically concentrated sludge is used, it is necessary to dilute it with water.
5. It is important to take care that flocculates will not leak into the outlet trough when filling the basin with inoculate sludge. The final concentration of the sludge in the WWTP should be 4-5 kg/m3
Adjustment of the air-supply inlet in the WWTP
After the membrane air-pump is switched on, the air distribution mechanism must be adjusted. The adjustment is done by regulating screws on the air-distribution element. The screws for the air-supply inlet into the aeration device must be left permanently open. They may be closed only in case of a defect on a particular part of the aeration system.
Adjustment of other parts of the air distribution device:
o the aeration of the screen-bar baskets is adjusted in such a way that every second the air will aerate the basket with a big bubble;
o the air-supply inlet into the recirculation mammoth pump is adjusted in such a way that 1/3 to 1/2 of the pump pipe is filled with a recirculated activated mixture.
7.4 Shut-down and re-starting into operation
Short-term intermission of the inflow into the WWTP will not disturb its' operation. If the inflow is interrupted for a longer period of time (more than 3 weeks) - e.g. during the holidays - it is necessary to shut down the WWTP or to dose a substitute organic liquid extract. At the time of a shut-down, it is advisable to interrupt the operation of the membrane-air pump often.
Shut-down of the WWTP
The contents of the WWTP are sucked out and the WWTP is cleaned (e.g. in case of seasonal work). Thereafter, the WWTP is filled with clean water.
Putting into operation
The WWTP is passed over to the operator as a serviceable unit. The installation and assembly of the WWTP is done by an authorized person who was trained by the manufacturer. Putting into operation is done in accordance with section No. 7.3 of these operational instructions.
- 8. Supervision and maintenance of the WWTP
- 8.1 Duties of the operator
- 8.1.1 Basic facts
The owner of the WWTP (the operator) is responsible for the quality of water which is discharged into a recipient. For this reason the operator is obliged to supervise the operation of the WWTP and to maintain it. Particular operations are done in accordance with this Service Manual (Operational Instructions). The operator orders technological inspection of the WWTP at a service organization approved by the manufacturer.
The basic supervision of the WWTP done by the operator involves the following steps:
- regular cleaning of the detritus trap (the screen-bar basket)
- inspection of the membrane-air pump; cleaning, possibly washing of the filter
- inspection of the mammoth for recirculation of activated mixture
- monitoring of concentration of activated sludge
- inspection of the mechanical-pollutant trap aeration
- inspection of the aeration of the activation zone
- inspection of the mixing process in the final clarification basin
- checking the amount of dissolved O2 in the inlet zone and in the activation zone of the WWTP (the inlet zone - 0 - 0.6 mg O2/l, activation zone 1.5 - 4 mg O2/l)
The WWTP must be operated and maintained throughout the year and an overall inspection must be performed at least twice a week. It is especially vital to check the membrane air-pump, clean the screen-bar basket, remove floating pollutants from the surface, and check and clean the floating-pollutant trap in the final clarification zone. Once a month, the construction of the WWTP and the technological equipment shall be inspected. The winter safety maintenance should be performed well in advance (maintenance, sludge disposal, preparation of gadgets for winter).
To ensure faultless operation of the WWTP the following substances should be avoided in the inlet:
- higher concentration of fat
- regenerative solutions from home softening agents
- colours, lacquers, diluters
- strong antiseptics, strong acids and alkalis
It is advisable to avoid the following mechanically and biologically undecomposable pollutants (to reduce the frequency of cleaning the detritus trap):
- plastic products
- rubber products
- textiles
8.1.2 Operating the WWTP
The WWTP is operated from the electro-box where the control unit is installed. Using mode A (see 8.1.3.) this control unit sets the membrane air-pump into permanent work mode. Work of the membrane air-pump and of the entire aerating system, as well as the electricity supply to the WWTP can be disconnected by a current protector.
- 8.1.3 Control Unit BCC-02
To carry out its functions, Control Unit BCC-02 has two working modes:
- Operating mode,
- Set mode.
The function of the unit in operating mode is among others related to a built-in clock. The running of the clock is backed up by a replaceable lithium battery, type CR2032 with life up to 20 years. The condition of the battery is continuously monitored, and when it is weak, the Control Unit displays a warning message.
The BCC-02 unit is intended to be installed in a switchboard box. During a usual installation, the terminals of the unit are covered by the switchboard, only the front of the unit, the controls, and indicating elements are accessible through a gap in the switchboard.

- The connection of the unit to a 230 V/50 Hz single-phase circuit and to device switches (through switch terminals KA1 to KA4) is illustrated in the picture. Controlled functions are assigned to relay terminals and to related screwing terminals as follows:
KA1 X1/1, X1/2 aeration activation
KA2 X1/5, X1/6 draw of clean water from the settling - compartment to the drain
KA3 X1/7, X1/8 settling compartment mixing
KA4 X1/9, X1/10 draw-off from the surface of the settling compartment
The circuit fuse location is also indicated in the picture. The fuse can be replaced after disconnecting the circuit and removing the fuse's cover.
Operating mode
The operating mode is the normal functioning mode of the BCC-02 unit. The unit is always in the operating mode after connecting to the circuit or when the set mode is finished. The operating mode is indicated by displaying time constants C1 to C6 in progress in the first two positions of the four-digit display and the number of minutes remaining to its completion (minutes countdown). These time intervals (periods) and their successions are important for the function in the operating mode:
C1 aeration period
C2 aeration interruption period
The succession of intervals C1 and C2 is repeated cyclically.
C3 cleaned water draw-off period
C4 the period of settling compartment mixing and simultaneous draw-off of floating substances
C5 delay between mixing and second draw-off of floating substances
C6 second draw-off of floating substances
Succession of linked intervals C3 to C6 is repeated in 12 or 24-hour periods.
- Set mode
The function of individual buttons in the set mode:
MODE
.. successively offers modes P1, P2, P3, START, TIME, Operating mode
+, -
change of set parameters, completion of period C3-C6 in START mode
SET
confirmation of selected mode or value of set parameter
A change of the unit's parameters is executed from the control panel in modes P1 to P3. A brief push of the MODE button indicates P1 mode, and each following brief push changes the mode offer in the sequence of P2, P3, START, TIME, Operating mode, P1, P2, ... and around again. Together with the mode, the set value of the parameter is displayed at the 3rd and 4th position of the display. To select the currently displayed mode, push the SET button.
The value of the parameter of the selected mode starts to flash and you can change the value with the - or + buttons. Always confirm the new value of the parameter by pushing the SET button. ´This concludes a change of parameters and you can either leave the unit as is (after 30 seconds of inactivity the unit switches back to Operating mode) or continue setting by pushing the MODE button.
P1 Mode
In the P1 mode select a pair of time intervals C1 and C2 by selecting codes 0 to 9 according to the following table, which is part of an operating program.